Tencent distributed cloud's time from customer order to solution to the customer

2024-06-11 11:36:31 浏览数 (2)

Although the Distributed Cloud uses public cloud technology and products, it needs to be delivered to the customer data center. You cannot apply at any time like a public cloud, and you can get cloud resources at any time. Therefore, during the pre -sale stage, customers will pay attention to the delivery cycle of the project.

There are two types of local schemes of Tencent Cloud. There are two types of CDC and CDZ. From customer order to final delivery to customer data center, the overall delivery cycle and delivery process are as follows:

CDZ, a large cloud demand scenario for customers in the local area. The delivery time is about 2 to 3 months, and it is necessary to strictly follow the Tencent IDC implementation standards and construction processes (such as rack disaster capacity, wiring standards), and need to be opened to Tencent Cloud Region Line. The delivery process involves process survey-> Equipment to the scene-> Senitors settled-> network equipment on the shelves-> server on the shelves-> special line to open-> software deployment-> acceptance.

CDC, for customers in local small and medium -sized cloud demand scenes and marginal cloud demand scenes. The delivery time is about 2 to 4 weeks. The implementation standards can be simplified according to the customer IDC. The delivery process involves process survey-> Equipment admission-> Construction staff enrollment-> Equipment on the shelf-> VPN opening-> software deployment-> acceptance.

0 人点赞